Information class:

Standard

 

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

This report has been prepared solely for use by the party which commissioned it (the ‘Client’) in connection with the captioned project. It should not be used for any other purpose. No person other than the Client or any party who has expressly agreed terms of reliance with us (the ‘Recipient(s)’) may rely on the content, information or any views expressed in the report. We accept no duty of care, responsibility or liability to any other recipient of this document. This report is confidential and contains proprietary intellectual property.

No representation, warranty or undertaking, express or implied, is made and no responsibility or liability is accepted by us to any party other than the Client or any Recipient(s), as to the accuracy or completeness of the information contained in this report. For the avoidance of doubt this report does not in any way purport to include any legal, insurance or financial advice or opinion.

We disclaim all and any liability whether arising in tort or contract or otherwise which it might otherwise have to any party other than the Client or the Recipient(s), in respect of this report, or any information attributed to it.

We accept no responsibility for any error or omission in the report which is due to an error or omission in data, information or statements supplied to us by other parties including the client (‘Data’). We have not independently verified such Data and have assumed it to be accurate, complete, reliable and current as of the date of such information.

Forecasts presented in this document were prepared using Data and the report is dependent or based on Data. Inevitably, some of the assumptions used to develop the forecasts will not be realised and unanticipated events and circumstances may occur. Consequently Mott MacDonald does not guarantee or warrant the conclusions contained in the report as there are likely to be differences between the forecasts and the actual results and those differences may be material. While we consider that the information and opinions given in this report are sound all parties must rely on their own skill and judgement when making use of it.

Under no circumstances may this report or any extract or summary thereof be used in connection with any public or private securities offering including any related memorandum or prospectus for any securities offering or stock exchange listing or announcement.

 

Contents

Executive Summary                                                                                                         

1       Introduction                                                                                                              

1.1     Introduction                                                                                                        

2       Project Organization and Construction Progress                                              

2.1     Project Organization                                                                                           

2.2     Construction Progress                                                                                         

2.3     Summary of Environmental Submissions                                                              

3       Construction Noise Monitoring                                                                              

3.1     Monitoring Requirements, Frequency and Duration                                               

3.2     Monitoring Locations                                                                                           

3.3     Monitoring Equipment                                                                                         

3.4     Monitoring Methodology                                                                                      

3.5     Monitoring Schedule                                                                                           

3.6     Results of Impact Monitoring                                                                               

4       Ecology Monitoring                                                                                                 

4.1     General                                                                                                              

4.2     Monitoring Requirement                                                                                      

4.3     Inspection Findings                                                                                             

4.4     Conclusion                                                                                                         

5       Landscape & Visual Monitoring                                                                            

5.1     General                                                                                                              

5.2     Inspection Findings                                                                                             

6       Waste Management                                                                                               

6.1     General Waste Management                                                                               

6.2     Records of Waste Quantities                                                                               

7       Site Inspection                                                                                                         

7.1     Requirements                                                                                                     

7.2     Findings / Deficiencies During the Reporting Period                                              

8       Environmental Complaint, Summons and Prosecution                                    

8.1     Environmental Complaint, Summons and Prosecution                                           

9       Implementation Status of Mitigation Measures                                                  

9.1     General Requirements                                                                                        

9.2     Tentative Construction Activities in the Coming Month                                           

9.3     Key Issues for the Coming Month                                                                        

10     Recommendation                                                                                                    

A.      Project Location                                                                                                       

B.      Project Organisation                                                                                               

C.      3-month Look-ahead Program                                                                              

D.      Designated Monitoring Locations as Recommended in the Approved EM&A Manual         

E.      Actual Locations of Impact Monitoring                                                                 

F.      Calibration Certificates                                                                                           

G.      Event and Action Plan                                                                                            

H.      Impact Monitoring Schedule                                                                                  

I.        Noise Monitoring Data                                                                                            

J.       Graphical Plots for Noise Monitoring Data                                                          

K.      Meteorological Data                                                                                                

L.      Ecological Inspection Records                                                                              

M.     Waste Flow Table                                                                                                   

N.      Implementation Schedule for Environmental Mitigation Measures                 

 

 

 

 

 

 

 

 


Executive Summary

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Gammon Engineering & Construction Company Limited, to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for Ocean Park Tai Shue Wan Development Water World.

This is the 11th monthly EM&A report for the construction phase of Waterpark Main Building Works submitted under Condition 3.4 of the Environmental Permit (No. EP-487/2014/A). This report summarises the findings on EM&A during the period from 1 to 30 April 2018.

Exceedance of Action and Limit Levels

The summary of measured noise level (as Leq) is presented in Section 3. No exceedance of Action or Limit Levels for noise levels were recorded in the Reporting Period.

Result of Ecological Monitoring

The plant species of conservation interest – Two numbers of Platycodon grandifloras was found in fence up area in the Reporting Period. No sign of construction activities was noted in the fence up area. 

No ardeids nest or potential breeding activities were observed..

Details of the results are presented in Section 4.

Result of Landscape and Visual Monitoring

No non-compliance of Landscape and Visual monitoring was recorded in the Reporting Period. Details of the results are presented in Section 5.

Record of Complaints

There was no record of complaints received in the Reporting Period.

Record of Notification of Summons and Successful Prosecutions

There were no record of notification of summons and successful prosecution in the Reporting Period.

Reporting Changes

There are no reporting changes.

Site inspection

In the Reporting Period, joint site inspections were undertaken by the PMR, ET and the Contractor on 6, 13, 20 and 27 April 2018. Furthermore, IEC performed the site inspection and audit on 13 April 2018. During site inspection, non-compliance was not observed by the ET and IEC.

Future Key Issues

    Site formation for ride footing construction

    Cut soil slope and soil nail installation for Ride P1, P2, P3, P4 and P5

    Rock breaking and slope stabilization works for Ride P1 to P5 

    Construction of drainage channels to slopes

    Mini pile construction

    Utilities diversion at A4

    Drainage works at PJD office and A4

    Backfilling at South Plant Room

    North Plant Room: Removal of falsework, waterproofing for double slab, concreting for high level slab and ABWF

    Main Building: L1 and L2 slab, column and wall construction, L3 column for Roof construction, Steel ramp for Platform construction, B1 underground manhole, drainage and on grade slab.  Block works and ABWF in B1, L1 and L2 Secondary structure construction.

    South Transformer Room:  Removal of falsework and ABWF

    South Plant Room: Construction of wall and plinths

    Spiral Ramp: On grade slab and Falsework for the RC construction.

 

 

1        Introduction

1.1        Introduction

On 27 August 2014, the Environment Impact Assessment (EIA) Report and Environmental Monitoring and Audit (EM&A) Manual (Register No.: AEIAR-184/2014) for the “Tai Shue Wan Development at Ocean Park” (the Project) was approved and an Environmental Permit (EP) (Permit No.: EP-487/2014) was issued to the Ocean Park Corporation (Project Proponent).

The current valid EP (Permit No.: EP-487/2014/A) was issued on 10 January 2018 based on the Variation of Environmental Permit No. VEP-539/2017 which comprise variation of project boundary, location of sump pit and size of rising main. The Project location is indicated in Appendix A.

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Gammon Engineering & Construction Company Limited to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit for the Ocean Park Tai Shue Wan Water World Project.

As part of the EM&A program, baseline monitoring for the required parameters including background noise, landscape & visual baseline review and baseline ardeid inspection were carried out between 24 October 2014 and 10 December 2014 by the environmental consultants of Ocean Park Corporation. Furthermore, the baseline monitoring report which verified by the previous IEC was submitted to EPD and endorsed in December 2014.

The previous contract (Contract No.: TSW-C004) of Site Formation and Foundation Works has been completed since 31 May 2017, the next construction phase (Contract No.: TSW-C006) for the Ocean Park Tai Shue Wan Development was handed over to Gammon Engineering & Construction Company Limited on 31 May 2017. This is 11th monthly EM&A report presenting the monitoring results and inspection findings for the Construction Phase of Waterpark Main Building Works during the Reporting Period from 1 to 30 April 2018.


 

2        Project Organization and Construction Progress

2.1        Project Organization

The project organization is shown in Appendix B.  The responsibilities of respective parties are: 

Ocean Park Corporation 

Ocean Park Corporation is the Project Proponent and the Permit Holder of the EP for the development of the Project and will assume overall responsibility for the project.  An Independent Environmental Checker (IEC) shall be employed by Ocean Park Corporation to audit the results of the EM&A works carried out by the ET. 

Environmental Protection Department (EPD) 

EPD is the statutory enforcement body for environmental protection matters in Hong Kong.

Project Management Representative (PMR) of Ocean Park Corporation 

The PMR is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the ER with respect to EM&A are: 

    Monitor the Contractors’ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness 

    Monitor Contractors’, ET’s and IEC’s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual 

    Facilitate ET’s implementation of the EM&A programme  

    Participate in joint site inspection by the ET and IEC  

    Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance 

    Adhere to the procedures for carrying out complaint investigation  

    Liaison with the related government departments, ET, IEC, the Contractor and the other 

Contractors of the Project discussing regarding the cumulative impact issues.  

The Contractor 

The duties and responsibilities of the Contractor are: 

    Comply with the relevant contract conditions and specifications on environmental protection  

    Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of EM &A Facilitate ET’s monitoring and site inspection activities  

    Participate in the site inspections by the ET and IEC, and undertake any corrective actions  

    Provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts  

    Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans  

    Implement measures to reduce impact where Action and Limit levels are exceeded 

    Adhere to the procedures for carrying out complaint investigation  

Environmental Team (ET) 

The ET should be employed by the Contractor to conduct the EM&A programme. The ET should be managed by the ET Leader.  ET Leader should have relevant professional qualifications in environmental control and possess at least seven years’ experience in EM&A. Suitably qualified professional and technical staff should be included in the ET, and resources for the implementation of the EM&A programme should be allocated in the time under the Contract, to enable fulfilment of the Project’s EM&A requirements as specified in the EM&A Manual during construction of the Project. The ET shall include qualified botanist/ecologist for the ecological service and a Registered Landscape Architect for review of implementation of landscape and visual mitigation measures. The ET should report to the OPC and the duties should include:

    to monitor and audit various environmental parameters as required in the Approved EM&A Manual; 

    to analyse the EM&A data, review the success of EM&A programme and the adequacy of mitigation measures implemented, confirm the validity of the EIA predictions, and identify any adverse environmental impacts arising; 

    to monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications; 

    to audit environmental conditions on site; 

    to report on the EM&A results to EPD, the ER, the IEC and Contractor or their delegated representatives; 

    to recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans; 

    to liaise with the IEC on all environmental performance matters, and ensure timely submission of all relevant EM&A pro forma for IEC’s approval; 

    to provide advice to the Contractor on environmental improvement, awareness and enhancement matters, etc on site; 

    to adhere to the procedures for carrying out complaint investigation; 

    to prepare reports on the environmental monitoring data and the site environmental 
conditions; 

    to submit the EM&A report to Director of Environmental Protection (DEP) timely; 

    to review proposals of mitigation measures from the Contractor in case of exceedance of Action and Limit levels, in accordance with the Event and Action Plan; and 

    to carry out site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and mitigation measures.

 

Independent Environmental Checker (IEC)   

    The IEC is empowered to audit the environmental performance of construction, but is independent from the management of construction works.  As such, the IEC should not be in any way an associated body of the Contractor or the ET for the Project.  The IEC should be 
employed by OPC prior to the commencement of the construction of the Project.  The IEC 
should be a person who has relevant professional qualifications in environmental control and at least seven years’ experience in EM&A and environmental management. The duties and 
responsibilities of the IEC are: 

    to provide proactive advice to the ER and OPC on EM&A matters related to the project; 

    to review and verify the monitoring data and all submissions in connection with the EP and EM&A Manual submitted by the ET; 

    to arrange and conduct regular, at least monthly site inspections of the works during the construction phase, and to carry out ad hoc inspections if significant environmental problems 
are identified; 

    to check compliance with the agreed Event and Action Plan in the event of any exceedance; 

    to check compliance with the procedures for carrying out complaint investigation; 

    to check the effectiveness of corrective measures; 

    to feedback audit results to the ET by signing off relevant EM&A pro forma; 

    to check that mitigation measures are effectively implemented; 

    to report the works conducted, and the findings, recommendations and improvements of the site inspections, after reviewing ET’s and Contractor’s works, the ER and OPC on a monthly basis; 

    to verify the investigation result of the environmental complaint cases and the effectiveness of corrective measures; 

    to verify EM&A report that has been certified by the ET leader; and 

    to audit EIA recommendations and requirements against the status of implementation of environmental mitigation measures on site.

2.2        Construction Progress

The construction program is enclosed in Appendix C.  In the Reporting Period, the major construction activity conducted under the Contract is summarized below:

    Site formation for ride footing construction

    Cut soil slope and soil nail installation for Ride P1, P2, P3, P4 and P5

    Rock breaking and slope stabilization works for Ride P1 to P5 

    Construction of drainage channels to slopes

    Mini pile construction

    Utilities diversion at A4

    Drainage works at PJD office

    Skin wall construction for Tress boulder at entrance

    North Plant Room: HKE West Substation slab falsework and formwork, rebar, and casting, East substation walls and double slab and L1 HL falsework, formwork, rebar, and casting.

    North Plant Room: Build walls, L1 HL and L2 slab. ABWF for the plant room.

    L2 Slab at Area 10E4: Construct remaining columns below L2, falsework, formwork, and rebar for Level 2 slab. Cast concrete, Dismantle the 10E4 falsework.

    L2 to L3 columns at Area 10E4: column, rebar, shutter, and casting of columns.

    Main Building: L1 and L2 slab, column and wall construction, L3 column for Roof construction, Steel ramp for Roof construction, B1 underground manhole, drainage and on grade slab.  Block works and ABWF in B1

    South Plant Room: On grade slab and construction of footing and wall

2.3        Summary of Environmental Submissions

Summaries of validity permits, licenses, and/or notifications on environmental protection for the Project are presented in Table 1. 

Table 1: Status of Environmental Licenses and Permits of the Project

Type of Permit/ License 

Submission Date

Reference/ 

License No. 

Date of Issue 

 

Date of Expiry 

Status

Environmental Permit

/

EP-487/2014/A

10-Jan-18

N/A

Valid

Variation of Environmental Permit

18-Dec-17

VEP-539/2017

10-Jan-18

N/A

Valid

Environmental Permit

/

EP-487/2014

27-Aug-14

N/A

Superseded

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

15-Mar-17

414651

N/A

N/A

Valid

Application for a Billing Account for Disposal of Construction Waste

14-Dec-16

Account No. 7026786

28-Dec-16

N/A

Valid

Discharge Licence under WPCO
WT00028196-2017

15-Mar-17

414650

29-May-17

31-May-22

 

Valid

Registration as a Chemical Waste Producer
(WPN: 5213-176-G2785-01)

21-Apr-17

415966

31-May-17

N/A

Completed

Construction Noise Permit under NCO
GW-RS0439-17

26-Apr-17

416080

15-May-17

29-Dec-17

Superseded

Construction Noise Permit under NCO

GW-RS0825-17

8-Sep-17

420985

22-Sep-17

21-Mar-18

Superseded

Renew Construction Noise Permit under NCO

GW-RS1024-17

3-Nov-17

422922

21-Nov-17

16-May-18

Valid

Renew Construction Noise Permit under NCO

GW-RS0356-18

16-Apr-18

432628

30-Apr-18

16-Nov-18

Valid

 

In accordance with the EP stipulation, the required documents submitted to EPD for retention are as listed below:

    Project Layout Plans 

    Management Organization of Main Construction Companies 

    Detailed Vegetation Survey Report 

    Woodland Compensation Plan 

    Ardeid Inspection Report 

    Short-nosed Fruit Bat Inspection Report 

    Baseline Monitoring Report Revision A of the Project

 


 

3        Construction Noise Monitoring

3.1        Monitoring Requirements, Frequency and Duration

Construction noise is one of the key environmental issues during the construction phase of the Project in accordance to the approved EM&A Manual. Following the requirements in the EM&A Manual, continuous noise monitoring for A-weighted levels Leq, L10, L90 shall be undertaken once per week during the construction phase. Measurement of Leq(30min) between 07:00-19:00 hours on normal weekdays.

If construction works are necessary to be carried out at other time periods, i.e. restricted time period (19:00-07:00 the next morning and whole day on public holidays) (hereinafter referred as “the restricted hours”), three consecutive Leq(5min) measurements shall be recorded, while complying specific conditions as stipulated on the Construction Noise Permit (CNP). Supplementary information for data auditing and statistical results such as L10 and L90 shall also be obtained for reference. Summary of these monitoring requirements is shown in Table 2.

Table 2: Noise Monitoring Parameters

Monitoring Station

Parameters

NM1A and NM2

      Leq(30min) on normal working days (Monday to Saturday) 07:00-19:00 except public holiday;

      3 sets of consecutive Leq(5min) during restricted hours i.e. 19:00 to 07:00 next day, and whole day of public holiday or Sunday when applicable, and

      Supplementary information for data auditing and statistical results such as L10 and L90 shall also be obtained for reference

The baseline results form the basis for determining the environmental acceptance criteria for the impact monitoring. According to the approved EM&A Manual with baseline monitoring results, construction noise criterion, namely Action and Limit levels proposed are listed in Table 3.

Table 3: Action and Limit Levels for Construction Noise

Monitoring Location

Action Level

Limit Level in dB(A)

NM1A and NM2

When one or more documented

complaints are received

70 dB(A)1,2

Note:      1. Acceptable noise levels for school should be reduced to 65 dB(A) during examination period
2. If works are to be carried out during restricted hours, the conditions stipulated in the CNP must be followed.

3.2        Monitoring Locations

Two designated noise monitoring locations as established in the EM&A Manual is shown in Appendix D.  After the baseline monitoring, alternative location NM1A has been proposed by MMHK due to rejection of the monitoring location set up at NM1. The proposal was verified and agreed by EPD in the Baseline Monitoring Report.

The construction noise monitoring locations for the Project are shown in Table 4 and Appendix E

Table 4: Impact Monitoring locations

Monitoring location

Descriptions

Type of measurement

NM1A

Slope near Victoria Shanghai Academy (VSA) to replace NM1 of the VSA

Free field

NM2

Hong Kong Juvenile Care Centre (HKJCC)

Facade

3.3        Monitoring Equipment

Integrating sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked using an acoustic calibrator. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in ms-1. The acoustic calibrator and sound level meter to be used in the impact monitoring will be calibrated yearly.

Noise monitoring equipment used for monitoring is listed in Table 5.

Table 5: Noise Monitoring Equipment

Equipment

Model

Integrating Sound Level Meter

Rion NL-52

Calibrator

Larson Davis CAL200

Portable Wind Speed Indicator

Anemometer/ Lutron AM-4201

3.4        Monitoring Methodology

Field Monitoring

    Sound Level Meter was set up on a tripod at a height of at least 1.2 m above ground.

    Noise measurements were taken in terms of the A-weighted equivalent sound pressure level (Leq) measured in decibels (dB). Supplementary statistical results (L10 and L90) were also obtained for reference.

    Free field measurement was made at NM1A while facade measurement was made at NM2.

    The battery condition was checked to ensure the correct functioning of the meter.

    Prior to and after each noise measurement, the meter was calibrated using an acoustic calibrator for 94 dB at 1 kHz. The checking was performed before and after the noise measurement.

    During the monitoring, all noise measurements would be performed with the meter with Fast time weighting and on the A-weighted equivalent continuous sound pressure level (Leq). Leq(30min) as the monitoring parameter for the time period between 0700-1900 hours on weekdays; and also Leq(15min) in three consecutive Leq(5min) measurements would be used as monitoring parameter for other time periods (e.g. during restricted hours), if necessary. In addition, any site observations and noise sources were recorded on a standard record sheet.

    A correction of +3 dB(A) was made to the free field measurement.

    Noise measurements were not made in fog, rain, wind with a steady speed exceeding 5 ms-1 or wind with gust exceeding 10 ms-1.

 

 

Equipment calibration

    The sound level meter and calibrator are calibrated and certified by a HOKLAS accredited laboratory at yearly intervals.

    Calibration records of sound level meter and calibrator, together with the Anemometer used for impact monitoring program in the Reporting Period are shown in Appendix F.

Meteorological Information

Meteorological information was extracted from “the Hong Kong Observatory Wong Chuk Hang Station” to provide the humidity, wind speed, wind direction and temperature etc. as background weather information. The meteorological data throughout the impact monitoring period is summarized in Appendix K.

Derivation of Action/Limit (A/L) Levels

According to the approved EM&A Manual and baseline monitoring results, Action and Limit levels criterion proposed for construction noise monitoring are listed in Table 6.

Table 6: Action and Limit Levels for Construction Noise

Monitoring Location

Action Level 

Limit Level in dB(A) 

 

Time Period: 07:00-19:00 hours on normal weekdays

NM1A and NM2 

When one or more documented complaints are received

70 dB(A) 1, 2

Note:    1. A correction of +3dB(A) was made to the free field measurement at monitoring station NM1A.
2. No examination has taken place during this reporting period.

Should non-compliance of the environmental quality criteria occur, remedial actions will be 
triggered according to the Event and Action Plan which is presented in
Appendix G. 

Data Management and Data QA/QC Control 

All monitoring data will be handled by the ET’s in-house data recording and management system. The monitoring data recorded in the equipment will be downloaded directly from the equipment at the end of each monitoring day.  The downloaded monitoring data will be inputted into a computerized database properly maintained by the ET. 

3.5        Monitoring Schedule

Monitoring for noise levels due to construction work was undertaken in compliance with the EM&A manual during the Reporting Period. Regular monitoring surveys were carried out on 4, 10, 19 and 26 April 2018 during the Reporting Period and three additional impact monitoring for the construction works held during restricted hour period on 1, 8, 15, 22 and 29 April 2018 to access the compliance with environmental requirements. A total of eighteen noise monitoring surveys were carried out at the two noise monitoring locations.

3.6        Results of Impact Monitoring

As shown in Table 7, results of the noise monitoring measurement were below 70 dB(A). No noise complaints were received in this Reporting Period. No exceedance (Action/Limit Level) of construction noise was recorded in this period.

Table 7: Summary of Construction Noise Monitoring Results (Noise level for 30 minutes)

Monitoring date

Time

 

Mean and range of noise levels, dB(A)

Limit Level for Leq (dB(A))2

Start

Finish

Leq (30min)

Corrected Leq(30min)1

NM1A

 

 

 

 

 

04-Apr-18

09:42

10:12

55.6

58.6

70

10-Apr-18

09:40

10:10

55.6

58.6

70

19-Apr-18

11:10

11:40

55.9

58.9

70

26-Apr-18

10:22

10:52

56.7

59.7

70

NM2

 

 

 

 

 

04-Apr-18

09:21

09:51

52.2

-

70

10-Apr-18

10:30

11:00

52.1

-

70

19-Apr-18

10:30

11:00

51.2

-

70

26-Apr-18

09:40

10:10

51.7

-

70

Note:      1. A correction of +3 dB(A) was made to the free field measurement at monitoring station NM1A.
2. No examination has taken place in this reporting period.

As shown in Table 8, results of the additional noise monitoring measurement were below 70dB(A). No exceedance (Action/Limit Level) of construction noise was thus recorded in this period.

Table 8: Summary of Construction Noise Monitoring Results (Noise level for 15 minutes)

Monitoring date

Time

 

Mean and range of noise levels, dB(A)

Limit Level for Leq (dB(A))2

Start

Finish

Leq (15min)

Corrected Leq(15min)1

NM1A

 

 

 

 

 

01-Apr-18

17:20

17:35

54.4

57.4

70

08-Apr-18

10:29

10:44

52.6

55.6

70

15-Apr-18

16:40

16:55

51.6

54.6

70

22-Apr-18

14:28

14:43

50.8

53.8

70

29-Apr-18

16:28

16:43

51.4

54.4

70

NM2

 

 

 

 

 

01-Apr-18

16:52

17:07

49.3

-

65

08-Apr-18

10:01

10:16

48.7

-

65

15-Apr-18

17:08

17:23

48.3

-

65

22-Apr-18

14:00

14:15

46.1

-

65

29-Apr-18

16:00

16:15

48.2

-

65

Note:       1. A correction of +3dB(A) was made to the free field measurement at monitoring station NM1A.
2. Technical memorandum on noise from construction work other than percussive piling – Section 4 Table 2.

Summary of data and the supplementary information for data auditing is presented in Appendix I. Graphical plots of the monitoring data are as shown in Appendix J.


 

4        Ecology Monitoring

4.1        General

As required under the Section 8.3.2 of the approved EM&A Manual, the implementation of ecological mitigation measures as detailed in the Section 15 of the EIA report and Appendix C of the approved EM&A Manual shall be routinely audited during the routine environmental audit; and any observations and recommendations shall be reported in periodic EM&A reports.

Among those mitigation measures recommended to avoid or minimize the disturbance to any plants of conservation interest (EM&A reference 8.3.1.1), nested ardeids (EM&A reference 8.3.1.2) and roosted short-nosed fruit bat (EM&A reference 8.3.1.3), the required inspection has already been undertaken in August / September 2014 with the results presented in the submitted respective baseline report.  Therefore, the following sections only address those applicable to this stage of the project, i.e., Section 8.3.2 of the approved EM&A Manual.

4.2        Monitoring Requirement

Monitoring of Plants of Conservation Interest (Platycondon grandiflorus) 

According to Condition 2.6 of Environmental Permit No. EP-487/2014, the Detailed Vegetation Survey Report has located two groups of the protected Platycodon grandiflorus and recommended that the plants should be protected with temporary protective fencing to avoid potential impact from construction activities (such as material storage), and monitor the identified Platycodon grandiflorus on a monthly basis throughout the construction phase to ensure they are not affected by the construction works of the Project. Accordingly, the following monitoring parameters will be undertaken on a monthly basis during the construction period:

    Effective implementation of the protection measures as recommended in the Section 4.1 of the Detailed Vegetation Survey Report 

    Monitoring of the two groups of Platycodon grandiflorus identified during the detailed vegetation survey to ensure they are not affected by the construction works

Monitoring of Nesting Activities of Ardeids in Breeding Season

The project area should be checked monthly in breeding season (April to July) for any potential breeding and nesting activities, and if required, suitably sized buffer area will be recommended to avoid human or machinery disturbance until the nest is abandoned.

Monitoring of Roosting Activities of Ardeids in Peak Wintering Season

The existing ardeid night roost within the project area should be monitored monthly during peak wintering season (November to March) during the construction phase by direct observation from a vantage point (i.e., point count method) in the evening from an hour before sunset to nightfall.

Compensation for Ardeid roosting Site

An enhancement area proposed as an alternative roosting site for ardeids should be developed during the first phase of the construction.

 

Compensation of Woodland Habitat

Mitigation measures recommended in the approved Woodland Compensation Plan should be fully and properly implemented, including but not limited to the creation of 0.84 ha woodland compensation on-site and 0.78 ha on-site woodland reinstatement, to mitigate for permanent loss of woodland habitat.

4.3        Inspection Findings

The ecological inspection was undertaken on 13 April 2018 by the qualified ecologist. The inspection findings are presented below.

Plants of Conservation Interest (Platycodon grandiflorus)

Platycodon grandiflorus is a perennial herb up to 120 cm tall. Stems erect with scarcely any branches. It is often found on sunny grassy hillslopes in brushes. Two groups of Platycodon grandiflorus (see Figure 1 of Appendix L for their locations) that were recorded in 2015’s growing season within the fenced area.

On the other hand, the preventive mitigation measures, i.e., erecting of temporary protective fencing and sign post, were found to be effectively implemented for human disturbance (see Photo 3 of Appendix L of this report), and there are no signs or evidence (e.g. dust coating of plant) to prove that the on-going construction activities within the Project Area has affected the health condition of the Platycodon grandiflorus. The new shoots were observed from the underground part in Reporting Period (see Photos 1 and 2 of Appendix L of this report).

Nesting Activities of Ardeids in Breeding Season

No signs or breeding (such as courtship, nest building, brooding, juveniles etc.) of ardeids were noted within the project area during the reporting month.

Roosting Activities of Ardeids in Peak Wintering Season.

In accordance with the approved EM&A Manual, this monitoring parameter would not be required beyond the Peak Wintering season, i.e., from 1st November to 31st March. The last monitoring event for roosting activities of ardeids in Peak Wintering Season 2018’s was undertaken on 16 March 2018.

Compensation for Ardeid roosting Site

To be implemented. 

Compensation of Woodland Habitat 

To be implemented. 

4.4        Conclusion

The implementation of the mitigation measures for the plant species of conservation interest, i.e., erecting of temporary protective fencing and sign post during the Reporting Period was noted. Platycodon grandifloras new shoots were observed from the underground part in the Reporting Period.

On the other hand, no sighting of ardeids or signs of any breeding/nesting activities were noted within the project area during the monitoring.

The tentative ecological inspection and monitoring in the next Reporting Period is scheduled on 11 May 2018.

5        Landscape & Visual Monitoring

5.1        General

 

Landscape and visual mitigation measures for the construction phase are listed in the Approved EM&A Manual Table 9.1.

The design, implementation and maintenance of landscape and visual mitigation measures shall be checked bi-weekly to ensure that they are fully realized during the construction phase. The scope of the site audit during construction shall include the following:

    The extent of the agreed works areas should be regularly checked. No construction activities or storage shall be undertaken outside the limit of the works; 

    The progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken; 

    All landscaping works are carried out in accordance with the specifications; and 

    All new plantings are carried out properly and during the right season.

Any potential conflicts between the proposed landscape and visual mitigation measures and any other project works or operational requirements shall be recorded for the Contractor to resolve in an early stage, without compromising the intention of the mitigation measures.

5.2        Inspection Findings

In the Reporting Period, bi-weekly landscape and visual site inspections were conducted on 6 and 20 April 2018.

According to the bi-weekly site inspections, it was observed that the Contractor complied with the intended aims of the mitigation measures, for example, neither construction activities nor materials storage conducted and placed outside of the working site boundary.

 


 

6        Waste Management

6.1        General Waste Management

Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time.

6.2        Records of Waste Quantities

All types of waste arising from the construction work are classified into the following: 

    Construction & Demolition (C&D) Material; 

    Chemical Waste; 

    General Refuse; and 

    Excavated Soil. 

 

Monthly Summary Waste Flow Table provided by the Contractor is shown in Appendix M. Materials were reused on-site as far as practicable.


 

7        Site Inspection

7.1        Requirements

According to the approved EM&A Manual, the environmental site inspection shall be formulated by the ET Leader. Weekly environmental site inspections should be carried out to confirm the environmental performance.

7.2        Findings / Deficiencies During the Reporting Period

In the Reporting Period, joint site inspections were undertaken by the PMR, ET and the Contractor on 6, 13, 20 and 27 April 2018. Furthermore, IEC performed the site inspection and audit on 13 April 2018. 

During site inspections, non-compliance was not observed by the ET and IEC.  However, a total of three observations were recorded in the Reporting Period. The findings / deficiencies of the Project observed during the weekly site inspections are listed in Table 9.

Table 9: Summary of findings / deficiencies

Date

Findings / Deficiencies

Follow-up Status

13 Apr 2018

Fugitive dust was observed, appropriate mitigation measures should be undertaken.

Mitigation measures (water spraying) for fugitive dust were undertaken and the mixing shelter was removed.

20 Apr 2018

Chemical and oil containers observed without drip tray at L1 corridor next to EVA, at L2 next to EVA and L3.

Drip tray has been provided for chemical container at L1 near EVA and the chemical container were removed from the area at L2 next to EVA L3

27 Apr 2018

Oil container observed without drip tray at L2 grout station

The chemical container without drip tray was removed from L2 grout station

The Contractor has rectified the above deficiencies immediately or within deadline.  Therefore, the environmental performance of the Project managed by the Contractor with OPC was considered satisfactory.

Special attention shall be paid on the proper implementation of mitigation measures to prevent runoff flow to public area.

As a general reminder, dust mitigation measures should be enforced to prevent fugitive dust from haul road, idle slope work and construction activities; and the site tidiness should be maintained.  Furthermore, all chemical materials shall be stored in the designated area after use with drip tray.

8        Environmental Complaint, Summons and Prosecution

8.1        Environmental Complaint, Summons and Prosecution

No environmental complaint, summons and prosecution were received in the Reporting Period.  

The statistical summary for environmental complaints is presented in Table 10.

Table 10: Statistics for complaints, notifications of summons and successful  prosecutions

Reporting Period 

Cumulative Statistics

 

 

Complaints 

Notifications of summons

Successful prosecutions

This report month

0

0

0

 

The complaints received in relation to the environmental impact during March 2018 was investigated as follows:

Case 1: The complaint was about noise generated by construction equipment and construction vehicles movement at midnight from the construction site of Ocean Park Tai Shue Wan Water World Project.

Result of investigation: 

As informed by the Contractor:

    As Shum Wan Road, the only access to the construction site, experienced congested traffic during daytime, the planned concreting works had been extended beyond 19:00.

    Referring to the information provided by the site team, no works was carried out during the incident period.

    It is noted that the Contractor obtained a valid Construction Noise Permit (CNP No. CW-RS1024-17) permitting the use certain powered mechanical equipment (PME) including PME for concreting works during restricted hours between 23 November 2017 and 16 May 2018. The listed PME and no. of units have been strictly followed to CNP.

This complaint is unlikely to be related to the construction works on the project site due to no construction works was carried out during the incident period.

Case 2: The complaint was about traffic noise at Nam Long Shan Road related to Ocean Park night time operation.

According to the complainant, construction vehicles travelled along Nam Long Shan Road in the direction of Ocean Park for the past few years between the hours of 01:00 and 04:00. Furthermore, the complaint suspect that some of the vehicles were garbage trucks but according to FEHD’s reply, no garbage pick-up was conducted during this period.

Result of investigation: 

As informed by the Contractor:

    No construction vehicles were accessed from Nam Long Shan Road to Project Site since the commencement of this contract (TSW-C006).

    The site entrance at Nam Long Shan Road leading to the upper part of the sewage rising main under this project. However, there are no night works for this area since the commencement of this contract (TSW-C006).

Based on the above information, the complaint is considered unlikely to be related to the construction works at the project site.

 

9        Implementation Status of Mitigation Measures

9.1        General Requirements 

The environmental mitigation measures that were recommended in the Implementation Schedule for Environmental Mitigation Measures in the approved EM&A Manual covered the issues of dust, noise, water and waste and are presented in Appendix N.   

The Project shall be implementing the required environmental mitigation measures according to the approved EM&A Manual as subject to the site condition.  Environmental mitigation measures generally implemented by the Contractor in this Reporting Period are summarized in Table 11.

Table 11: Environmental Mitigation Measures 

Issues

Environmental Mitigation Measures

Construction 
Noise 

     Construction equipment shut down when not in use

Ecology

     Wire fencing was provided for temporary protection of the identified flora species of 
conservation concern 

     Site inspection of the flora species of conservation and the Ardeid 
of breeding and nesting activities was undertaken

Landscape & Visual

     Good site management

Air Quality

     Good site management to reduce air quality impact 

     Main temporary access road paved with concrete 

     Prior to any loading or transfer operation, all dusty materials were sprayed with water to keep them wet 

     All debris had been covered entirely by impervious sheeting 

     Before debris was dumped into a chute, water was sprayed onto the debris to make them wet 

     Vehicles were covered with tarpaulin during transport of dusty materials 

     When vehicles were leaving the construction site, any vehicles loaded with dusty materials were covered with clean impervious sheeting to prevent fugitive dusty material emission 

     The speed of the trucks passing site areas was controlled to below 10 km/hour 

     Water spraying was provided for soil-nailing work 

Water Quality

     Portable chemical toilets were provided on site

     A licensed collector has been employed to collect effluent and off-site dispose. 

Waste and Chemical Management

     A temporary container located far away from sea shore and drainage 
channel was provided for chemical materials and waste storage 

     Drip tray was provided for chemical materials at the working areas

     Waste skip was provided for general refuse disposal 

General

     The site was generally kept tidy and clean

 

9.2        Tentative Construction Activities in the Coming Month

Construction activities to be undertaken in the coming month for the Project are listed below:

    Site formation for ride footing construction

    Cut soil slope and soil nail installation for Ride P1, P2, P3, P4 and P5

    Rock breaking and slope stabilization works for Ride P1 to P5 

    Construction of drainage channels to slopes

    Mini pile construction

    Utilities diversion at A4

    Drainage works at PJD office and A4

    Backfilling at South Plant Room

    North Plant Room: Removal of falsework, waterproofing for double slab, concreting for high level slab and ABWF

    Main Building: L1 and L2 slab, column and wall construction, L3 column for Roof construction, Steel ramp for Platform construction, B1 underground manhole, drainage and on grade slab.  Block works and ABWF in B1, L1 and L2 Secondary structure construction.

    South Transformer Room:  Removal of falsework and ABWF

    South Plant Room: Construction of wall and plinths

    Spiral Ramp: On grade slab and Falsework for the RC construction.

9.3        Key Issues for the Coming Month

Based on construction activities as undertaken in the coming month, key environment issues consider to be included: 

    Potential fugitive dust impact due to the dry/loose/exposure soil surface/dusty material;

    Potential water quality impact due to surface runoff especially on the hillside;

    Potential wastewater impact due to dust suppression measures;

    Implement dust suppression measures at all times;

    Ensure noise and dust mitigation measures are implemented properly;

    Sediment catch-pits and silt removal facilities should be regularly maintained;

    Site effluent discharge shall be fulfilled the discharge license requirements;

    Proper implementation of the management of chemical wastes;

    Ensure chemical storage is managed properly;

    Implementation of construction noise preventative control measures; and

    Cleanliness and tidiness in construction site should be maintained properly.

10   Recommendation

    Dust mitigation measures for potential fugitive dust impact should be implemented in dry season.

    Noise mitigation measures, including the use of quiet plants, should be implemented in accordance with the EM&A requirement.

    Cleanliness and tidiness in construction site should be enhanced.

     

	